CHAPTER VI
DISTRIBUTION SYSTEM OPERATION
Article 52
European entity for distribution system operators
1. Distribution system operators shall cooperate at Union level through the EU DSO entity, in order to promote the completion and functioning of the internal market for electricity, and to promote optimal management and a coordinated operation of distribution and transmission systems. Distribution system operators who wish to participate in the EU DSO entity shall have the right to become registered members of the entity.
Registered members may participate in the EU DSO entity directly or be represented by a national association designated by the Member State or by a Union-level association.
2. Distribution system operators are entitled to associate themselves through the establishment of the EU DSO entity. The EU DSO entity shall carry out its tasks and procedures in accordance with Article 55. As an expert entity working for the common Union interest, the EU DSO entity shall neither represent particular interests nor seek to influence the decision-making process to promote specific interests.
3. Members of the EU DSO entity shall be subject to registration and to the payment of a fair and proportionate membership fee that reflects the number of customers connected to the distribution system operator concerned.
Article 53
Establishment of the EU DSO entity
1. The EU DSO entity shall consist of, at least, a general assembly, a board of directors, a strategic advisor group, expert groups and a secretary-general.
2. By 5 July 2020, the distribution system operators shall submit to the Commission and to ACER, the draft statutes, in accordance with Article 54, including a code of conduct, a list of registered members, the draft rules of procedure, including the rules of procedures on the consultation with the ENTSO for Electricity and other stakeholders and the financing rules, of the EU DSO entity to be established.
The draft rules of procedure of the EU DSO entity shall ensure balanced representation of all participating distribution system operators.
3. Within two months of receipt of the draft statutes, the list of members and the draft rules of procedure, ACER shall provide the Commission with its opinion, after consulting the organisations representing all stakeholders, in particular distribution system users.
4. Within three months of receipt of ACER's opinion, the Commission shall deliver an opinion on the draft statutes, the list of members and the draft rules of procedure, taking into account ACER's opinion as provided for in paragraph 3.
5. Within three months of receipt of the Commission's positive opinion, the distribution system operators shall establish the EU DSO entity and shall adopt and publish its statutes and rules of procedure.
6. The documents referred to in paragraph 2 shall be submitted to the Commission and to ACER where there are changes thereto or upon the reasoned request of either of them. The Commission and ACER shall deliver an opinion in line with the process set out in paragraphs 2, 3 and 4.