(c) energy purchases or sales necessary for the operation of the transmission system.
9. The compliance officer shall monitor the compliance of the transmission system operator with Article 41.
10. The compliance officer shall have access to all relevant data and to the offices of the transmission system operator and to all the information necessary for the fulfilment of his task.
11. The compliance officer shall have access to the offices of the transmission system operator without prior announcement.
12. After prior approval by the regulatory authority, the Supervisory Body may dismiss the compliance officer. It shall dismiss the compliance officer for reasons of lack of independence or professional capacity upon request of the regulatory authority.
Article 51
Network development and powers to make investment decisions
1. At least every two years, transmission system operators shall submit to the regulatory authority a ten-year network development plan based on existing and forecast supply and demand after having consulted all the relevant stakeholders. That network development plan shall contain efficient measures in order to guarantee the adequacy of the system and the security of supply. The transmission system operator shall publish the ten-year network development plan on its website.
2. The ten-year network development plan shall in particular:
(a) indicate to market participants the main transmission infrastructure that needs to be built or upgraded over the next ten years;
(b) contain all the investments already decided and identify new investments which have to be executed in the next three years; and
(c) provide for a time frame for all investment projects.
3. When elaborating the ten-year network development plan, the transmission system operator shall fully take into account the potential for the use of demand response, energy storage facilities or other resources as alternatives to system expansion, as well as expected consumption, trade with other countries and investment plans for Union-wide and regional networks.
4. The regulatory authority shall consult all actual or potential system users on the ten-year network development plan in an open and transparent manner. Persons or undertakings claiming to be potential system users may be required to substantiate such claims. The regulatory authority shall publish the result of the consultation process, in particular possible needs for investments.
5. The regulatory authority shall examine whether the ten-year network development plan covers all investment needs identified during the consultation process, and whether it is consistent with the non-binding Union-wide ten-year network development plan (‘Union-wide network development plan’) referred to in point (b) of Article 30(1) of Regulation (EU) 2019/943. If any doubt arises as to the consistency with the Union-wide network development plan, the regulatory authority shall consult ACER. The regulatory authority may require the transmission system operator to amend its ten-year network development plan.
The competent national authorities shall examine the consistency of the ten-year network development plan with the national energy and climate plan submitted in accordance with Regulation (EU) 2018/1999.
6. The regulatory authority shall monitor and evaluate the implementation of the ten-year network development plan.